Miscellaneous finish carpentry items were milled and replaced. Major phases of work included:
|
Scope of Work: The project consisted of complete demolition of existing car port roof shingles, non‐functioning internal trough gutter, soffit, and selective trim. As a design/build project delivery, Troop inspected existing construction details to determine the cause of failure of existing construction and consulted owner on the best course of action for redesign and rework. The non‐functioning components of the roof system were removed to allow for new installation to the proper detail. A new ridge vent was cut in as well as new ice/water shield,shingles, gutters, and downspouts were installed. Value: $15,000.00 Architect reference available upon request. |