X

Forest Park USARC Boiler Replacement, Forest Park, IL

  • 07/01/2015
  • By admin
  • Comments Off on Forest Park USARC Boiler Replacement, Forest Park, IL
  • in

Scope of Work: This design / build project included the removal of two existing boilers and a 400 gallon expansion tank. New work included installation of 8 new energy efficient hot water boilers and 2 new 200 gallon expansion tanks. In addion to the equipment work, all design documents and engineering were generated and submied for approval. Associated work included: replacing all existing piping in the mechanical room, new controls and equipment pads; asbestos removal; repair to the exisng roof to allow for the new vents; and all patch/repair of existing surfaces. All new controls were installed along with comprehensive commission of all new equipment.
Definable features of work:

  • Asbestos (ACM) testing
  • Demolition
  • Mechanical/plumbing
  • Electrical
  • Commissioning

Value: $424,060; completed 12/2012
Client Reference: Diann Shim, AFOS, 708.209.2600 x 272

Contact us

Please feel free to contact us using the form below.

Troop Contracting Inc.
p: 630.568.5252
f: 773.525.0275

648 Executive Drive
Willowbrook, IL 60527